New Seattle NHL arena remains on schedule for summer of 2021

KeyArena

The interior of the existing roof of KeyArena, the only part of the structure that will remain during a major renovation of the building, stands above the construction site below of what will be NHL hockey team site during a tour for media members Monday, Sept. 16, 2019, at the Seattle Center in Seattle. (Elaine Thompson / AP)

SEATTLE — The arena for Seattle’s NHL expansion franchise remains on track to open sometime in the summer of 2021.

Construction officials said Monday that the entire bowl of the former KeyArena has been demolished and excavation work is ongoing. Officials hope to begin digging down 15 feet from the current floor by year’s end and to spend most of 2020 constructing the new seating bowl from the bottom up.

Ken Johnsen, who is overseeing the construction project for Oak View Group and the NHL franchise, says the most challenge part so far has been putting in supports to take on the weight of the 44 million-pound roof, which is staying in place. The new arena is being built under the roof, which has historical landmark status.

Johnsen says the budget for the project remains around $930 million.

When submitting content, please abide by our submission guidelines, and avoid posting profanity, personal attacks or harassment. Should you violate our submissions guidelines, we reserve the right to remove your comments and block your account. Sportsnet reserves the right to close a story’s comment section at any time.